The day

Six steps, and only the fourth one is the meeting

The meeting is half an hour. The day around it is five more steps, and most of what makes the half-hour work happens in them.

Six discs in a row: five identical brass ones and, in the fourth position, a worn wooden one raised on a block.
  1. 1 The sources ready, stale or missing
  2. 2 The card milestones, blockers, round
  3. 3 Three outputs post, agenda, sheet
  4. 4 The meeting half an hour, recorded
  5. 5 One pass summary and carry-forward
  6. 6 The outbox you press send
Six steps in a day. One of them is the meeting; the other five are before and after it. Nothing leaves the machine without a person having looked at it.

1 — The sources are checked, not assumed

Before anything is generated, a pre-flight prints one table of every declared source — the chat archive, the tracker archive, the status author's report — as ready, stale, failed or missing, with how far behind each one is. It exits non-zero if any is stale or missing.

It takes seconds against a full build of about three minutes, so it is what a scheduler runs.

The property that matters is the one in the negative: if a source is not there, the agenda says so instead of filling the gap.

2 — The agenda is generated as a card

/ops prepare first checks that the project's configuration still matches the project. Then it writes the agenda: the milestones, each with a date, a source and a state; the release blockers, read from the tracker's own labels; a confirmation block; and a one-minute round where each person's row is already filled.

The sources with their ages, the full carried list and the repository detail go to a separate details file, so the page the room looks at stays one page. That file belongs to whoever is leading: it exists so they can ask a better question, and it is never the room's material and never a measure of a person.

daily · tuesday 08:12 · sources: chat 40 min, tracker 2 h, report yesterday

Milestones

  • Beta to the test group 14 May on plan
  • Code freeze 21 May at risk
  • Release 28 May on plan

Release blockers

  • Sign-in stalls at two-factor blocker #id
  • The e-mailed receipt is empty critical #id

carried since yesterday · #id · source: the issue

Confirm

Are the dates right? Is any of the above closed since yesterday?

The round — a minute each

  • Person 1 open: sign-in stalls · waiting for a test: the e-mailed receipt
  • Person 2 open: the import drops the last row · waiting for a test: —
  • Person 3 open: — · waiting for a test: the time zone in the export
Invented data, drawn in code. A real card is a file in the project folder, and this page shows no screenshots of real files.

For a daily that is mostly about getting a release out, this shorter shape is a setting, not the default. The card form — movement of the release gap, dependencies, the decisions due — is what a weekly still gets.

3 — Three outputs, because there are three audiences

A short post for the chat, in plain text, a house rule of three to five lines. The shared agenda that goes up on screen. And the facilitator sheet.

The sheet is written by hand, every day, because turning a fact into the right question is judgement and the contract marks that step manual on purpose.

4 — The meeting

Half an hour, recorded. The person leading reads the milestones, confirms the blockers, runs the round at a minute each, and reads back the decisions with their owners before anyone leaves.

Everything asynchronous is invisible to a recorded meeting by construction, which is what the archives in step one are for.

How the recording gets into the session

  1. Paste it

    the text straight into the session

    no set-up

  2. Drop the file

    a .vtt or .txt in the folder

    no set-up

  3. Over MCP

    the session fetches the meeting from a knowledge base

    one provider, once

The loop does not care which route the text came by. It cares that the note names the source, because two recordings of one meeting is the normal case, and a note that cannot say which one it came from cannot be corrected against it.

For a meeting that happens once, any of the three is fine. For one that happens every working day, the third is the difference between an export step every morning and none at all: the session reads the meeting out of the knowledge base itself, with the speakers already separated and the back catalogue searchable.

Several providers do that job over MCP — Deep Thought, Klang and others are listed on the tools page. They are interchangeable on purpose: each one is an ingestor that produces text, and the framework is what decides what the text means.

5 — One pass over the recording, the same day

/ops process writes the summary, the changelog line, the task ledger and the observations, and archives the raw transcript. The summary's last section is the carry-forward, and each line on it carries a kind, an owner and a source anyone can open.

Tomorrow's agenda starts from that list. This is the step where the loop closes, and the only one that cannot be skipped without the rest degrading into a notebook.

6 — What goes out is staged, and its manifest is the record

Anything sent sits in an outbox folder with a manifest, and a dispatching surface delivers it and writes back only what it did.

The manifest's status is the only record that something went out, and a message is never edited after it has gone.

Needs a folder with the loop wired, archives the fetchers can reach, and a person who leads the meeting. Walkthrough two shows which of your folders are wired.

One project team, one month, written from that team's own agendas, daily notes and the change requests the month produced. The team is not named, and no measurement from its month is published here.